Total Phase Aardvark Pinout: I2C/SPI 10-Pin Connector

The Total Phase Aardvark I2C/SPI Host Adapter connects to your target through one 10-pin (2x5) header carrying both the I2C and SPI signals. The pinout, connector and electrical details below are taken from Total Phase's Aardvark user manual and datasheet.

Aardvark pinout at a glance: pin 1 SCL, pin 3 SDA, pin 5 MISO, pin 7 SCLK, pin 8 MOSI, pin 9 SS, pins 2 and 10 GND, pins 4 and 6 NC/+5V. The connector is a 2x5, 2.54 mm pitch IDC header with 3.3 V signal levels.

Aardvark 10-pin connector pinout

Pin Signal Function
1 SCL I2C clock
2 GND Ground
3 SDA I2C data
4 NC/+5V Optional +5 V target power
5 MISO SPI master in, slave out
6 NC/+5V Optional +5 V target power
7 SCLK SPI clock
8 MOSI SPI master out, slave in
9 SS SPI slave select
10 GND Ground

Connector, cable and orientation

The supplied ribbon cable ends in a standard 0.100 in (2.54 mm) pitch IDC socket that mates with a standard keyed 2x5 boxed header. The cable itself is 10-way, 0.050 in pitch and 131 mm long.

The red stripe on the cable marks pin 1. With the Aardvark upright, pin 1 is top left and pin 10 is bottom right. Always connect at least one GND pin (2 or 10) to the target ground.

Electrical characteristics

  • Signal levels are nominally 3.3 V logic high (plus or minus 10%).
  • Pins 4 and 6 can supply +5 V to the target. The supply is off when shipped and, on hardware v2.00 and later, is switched on in software. Total Phase specifies a maximum of 25 mA per pin, so use them for small evaluation boards only, not as a general supply.
  • The Aardvark fits a 2.2 kΩ pull-up resistor to SCL and SDA (switchable in software on hardware v2.00 and later), giving roughly 1.5 mA of pull-up current. If your board already has pull-ups, account for the parallel resistance.

Aardvark I2C and SPI wiring

For I2C, connect SCL (pin 1), SDA (pin 3) and GND (pin 2 or 10). For SPI, connect SCLK (pin 7), MOSI (pin 8), MISO (pin 5), SS (pin 9) and GND.

Same layout on other Total Phase tools

The Beagle I2C/SPI Protocol Analyzer uses the same signal positions, and pins 1 to 10 of the Promira Serial Platform's 34-pin connector follow the same I2C/SPI layout. The Cheetah SPI Host Adapter matches on the SPI pins but uses pins 1 and 3 for extra slave selects instead of I2C. Target wiring planned for the Aardvark therefore carries over directly to a Beagle I2C/SPI analyser for bus monitoring. Side-by-side tables for every tool are on our Total Phase I2C/SPI pinouts page.

Buy the Aardvark and accessories

Frequently asked questions

What is the Total Phase Aardvark pinout?

Pin 1 SCL, pin 2 GND, pin 3 SDA, pin 4 NC/+5V, pin 5 MISO, pin 6 NC/+5V, pin 7 SCLK, pin 8 MOSI, pin 9 SS and pin 10 GND, on a 2x5, 2.54 mm pitch IDC connector.

Which Aardvark pins are used for I2C?

SCL on pin 1 and SDA on pin 3, with ground on pin 2 or pin 10. The Aardvark fits 2.2 kΩ pull-ups to both lines.

Which Aardvark pins are used for SPI?

SCLK on pin 7, MOSI on pin 8, MISO on pin 5 and SS on pin 9, with ground on pin 2 or pin 10.

Can the Aardvark power my target board?

Pins 4 and 6 can supply +5 V, with a maximum of 25 mA per pin according to Total Phase. That suits small evaluation boards, not general supply duty.

Does the Beagle I2C/SPI analyser use the same pinout as the Aardvark?

Yes. The Beagle I2C/SPI uses the same signal positions, so target wiring planned for the Aardvark also works for bus monitoring. The Cheetah differs on pins 1 and 3, which carry extra slave selects.

Related Total Phase connection guides

Sources

Last reviewed 22 November 2026 by The Debug Store, supplier of Total Phase tools.